Resources & Energy (ASX:REZ) - Mining Operations at Granny Venn Begin

REZ

Highlights

  • Project Management Plan Approved. 
  • Clearing Permit and Water Abstraction Licenses have been approved. 
  • Near Term Production Target of 120kt for 8,800oz identified. 
  • First ore production scheduled for September. 
  • Toll Milling Agreements in place.

Resources & Energy Group Limited (ASX:REZ or the Company) advise that following approval of the Project Management Plan for Granny Venn, the first drill and blasting operations were carried out on Monday 5th July. A notification of Commencement of Operations will be lodged with DMIRS with first truck haulage out of pit expected on or about 9th July. The mining operations are being directed by BM Mining, who have been mobilising plant and equipment to site over the past few weeks. The project facilities include crew accommodation, office, mobile workshop and first aid room.  

Mining Operations at Granny Venn Commence.

Background

During March, the Granny Venn Open pit access ramp was rehabilitated, and the mine dewatered to expose the pit floor at completion of operations in 1998. A program of Grade Control Drilling was subsequently carried out. A total of 68 holes were drilled within the footprint and periphery of the Granny Venn Open cut for an advance of 1779m. 

In‐pit drilling operations focussed on a potential cut‐ back to exploit an interpreted extension to the main Granny Venn ore body in the north‐west and north‐east ends of the pit. Drilling in the ramp at the pit‐top end of the mine and in the adjacent Aunt Nellie pit was also carried out. The final results of this work were received and released in June (1). 

Mine planning by BM Mining has been updated to incorporate the new results, and a production schedule has been prepared. This schedule has identified a Near Term Production Target of 120kt @ 2.3gt/au for 8,800oz au distributed over 5 areas, refer figure 1. Based on the schedule, first ore production is expected to commence in Early August and the first Milling Campaign is programmed for September. This initial production campaign is scheduled for completion by late December.

The commencement of mine operations at Granny Venn is an important milestone for the company and is a credit to BM Mining who are managing Operations. Since acquiring the East Menzies Gold Project in late 2019, REZ has rapidly moved to assess near term production opportunities, whilst continuing to investigate greenfields and brownfields exploration targets with a view to discovering 1m oz plus of gold.

Presently, two areas of investigation are underway at Gigante Grande along the eastside of the Project area, which has delivered very encouraging results and Springfield on the west, which we have just opened up, refer figure 2. Work on expanding exploration across the broader project area has also commenced with over 9 walk up targets identified for initial drill investigations, 4 targets for near term resource generation and a further 21 targets for a combination of regional air core, soils geochemistry and geophysical enquiry. The project covers a known goldfield (Menzies) and has a rich history of delivering gold.

Figure 1 Location Plan showing Proposed Mining Areas and Site Layout

Next Steps

An analysis of historical exploration results around the perimeter of the Granny Venn Pit has also identified several shallow areas for follow up investigation with opportunity to add ounces to the Operation‐areas 3,4 and 5 shown on Figure 1. Drill testing these resource areas has commenced.

 

Read the full announcement here.

To keep up to date with their news and progress, and for more information about gold mining as a whole, subscribe to the Resources & Energy Group's Chairman's List.